Salto Grande 500 kV high-voltage power line

Im3 executes a basic and detailed engineering project to change the communications systems for 500 kV lines

The project included:

  • 159 km, 500 kV Salto-Colonia Elía line
  • 23 km, 500 kV Colonia Elía-San Javier line
  • 157 km, 500 kV Salto-San Javier line